[Transport]

ARGENTINA - Reactivation of Freight Train Roca Line (Norpatagonico Tren)

Summary

The project aims at enabling the development of the Vaca Muerta shale gas fields, which are an essential natural resource. The train redevelopment will allow more efficient transportation

Current Stage

Feasibility study

Duration

14 Years

Greenfield or Brownfield Project?

Brownfield

Type of PPP

Design-Build-Finance-Maintain (DBFM)

Source of Revenues

Payments from Users Minimum Revenue Guarantee Neuquen Province's Oil Royalties

Governmental Support

State Guarantees

Equity from the Provincial Government

AUSTRALIA - Capital Metro Light Rail

Summary

Delivery of 12 km light rail track, 13 stops and 14 light rail vehicles

Current stage

Construction

Duration

3 Years Delivery; 20 Years Operations

Estimated project cost

$939M

Greenfield or Brownfield project?

Greenfield

Source of revenues

Availability Payments

Governmental support

Territory Contribution of $375M payable upon achievement of completion

CANADA - Southwest Transitway Project

Summary

The project integrates maintenance of an existing 3.6km transit corridor with design, construction and maintenance of a 7.6km transitway from the central business district to the University of Manitoba, widening of an existing highway (Pembina) and the relocation of a Canadian National Railway Bridge

Current stage

Construction

Duration

30 Year Concession

Estimated project cost

$590M

Greenfield or Brownfield project?

Greenfield

Type of PPP

Design-Build-Finance-Maintain (DBFM)

Source of revenues

Availability Payments

Governmental support

Federal grant

GERMANY - "A 10/A 24, Neuruppin - Pankow"

Summary

The project comprises the widening from four to six lanes between Havelland and Pankow (29.6 km) as well as the full depth reconstruction of the four-lane motorway between Neuruppin and Kremmen (29.2 km)

Current stage

Construction

Duration

30 Years

Estimated project cost

€1,4 bn

Greenfield or Brownfield project?

Brownfield

Source of revenues

Initial Public Financing and Availability Payments

FRANCE - High speed rail Tours - Bordeaux (LGV SEA)

Summary

The project aims at bringing high-speed rail service to southwestern France and connecting the regions of Nouvelle-Aquitaine and Occitanie with the high-speed rail service of Northern Europe (Paris-London-Brussels-Amsterdam)

Current stage

Operational

Duration

50 years

Estimated project cost

€7,800M

Greenfield or Brownfield project?

Greenfield

Type of PPP

Concession

Source of revenues

User Payment

Governmental support

Public subsidies

State guarantees

INDIA - Widening of Jaipur-Kishangarh Road

Summary

The project aims at strengthening 2-lane highway from km 273 to km 364 on the Jaipur- Kishangarh section of national highwayNa 8 in Rajasthan, whichconnects Mumbai to Delhi and serves as the major artery connecting the ports in Maharashtra / Gujarat to the landlocked northern hinterland

Current stage

Operational

Duration

20 Years

Estimated project cost

INR 7,284M

Greenfield or Brownfield project?

Brownfield

Type of PPP

Build-Operate-Transfer (BOT)

Source of revenues

User Payment

Governmental support

Capital Grant in the form of Equity Support

INDONESIA - Makassar Parepare Railway Project

Summary

The project is part of Trans Sulawesi Railway Development and is guaranteed by Indonesia Infrastructure Guarantee Fund

Current stage

Contract Award

Duration

18.5 Years

Estimated project cost

$70M

Greenfield or Brownfield project?

Brownfield

Type of PPP

Build-Operate-Transfer (BOT)

Source of revenues

Government Payment

Governmental support

Project Development Facility, Guarantees

MEXICO - "Ferrocarril Suburbano Cuautitlan-Buenavista"

Summary

26 km railroad (double track), seven stations, 20 electric trains

Current stage

Operation

Duration

50 Years

Estimated project cost

$560M

Greenfield or Brownfield project?

Greenfield

Type of PPP

Build-Operate-Transfer (BOT)

Source of revenues

User Payment

Governmental support

Subsidies, Equity, Guarantees, Mezzanine Debt, Senior Debt

NETHERLANDS - Lock Extension in Eefden

Summary

The project aims at constructing a second lock chamber to connect the river IJssel with the Twente canal

Current stage

Construction

Estimated project cost

€115M

Greenfield or Brownfield project?

Brownfield

Type of PPP

Design-Build-Finance-Maintain-Operate (DBFMO)

Source of revenues

Availability Payments

NETHERLANDS - "The Afsluitdijk (Cut-off Dike) Project"

Summary

The project aims at strengthening the Afsluitdijk - Major Causeway in the Netherlands stretching from Den Oever on Wieringen in the North Holland province to the village of Zurich in the Friesland Province

Current stage 

Pre-construction

Duration

25 Years

Estimated project cost

$1785M

Type of PPP

Design-Build-Finance-Maintain (DBFM)

Governmental support

Federal grant

RUSSIA - "Western High-Speed Diameter" in St. Petersburg

Summary

Intracity toll motorway in St. Petersburg. The road is 46.6 km long and connects the Big Sea Port and the Ring Road of St. Petersburg providing exits to the Baltic countries, Scandinavia and other regions of Russia

Current stage

Operation

Duration

42 Years

Estimated project cost

RUB 212 720 bn

Greenfield or Brownfield project?

Greenfield

Type of PPP

Build-Operate-Transfer (BOT)

Source of revenues

User Payment along with Commercial Operations

Governmental support

General guarantees

Compensation of Private Partner's Expenses

RUSSIA - "Obskaya-Salekhard-Nadym" Public Rail

Summary

The project is an integral part of the comprehensive investment initiative "Creation of the Northern Latitudinal Railway "Obskaya - Salekhard - Nadym - Pangody - Novy Urengoy - Korotchaevo" and will result in the creation of the railway transport infrastructure, which is necessary to integrate economic and territorial subjects in the Arctic zone to the rest of Russia

Current stage

Pre-investment

Duration

35 Years

Estimated project cost

RUB 113 857 bn

Greenfield or Brownfield project?

Greenfield

Type of PPP

Build-Operate-Transfer (BOT)

Source of revenues

Availability Payment along with Commercial Operations 

Governmental support

General guarantees

Compensation of Private Partner's Expenses

SPAIN - "Autovi'a de la Plata "A-66 Benavente Zamora""

Summary

Construction, operation and maintenance of Highway A-66 Benavente Zamora 

Current stage

Operational and Maintenance

Duration

30 Years

Estimated project cost

€205M

Greenfield or Brownfield project?

Greenfield

Type of PPP

Build-Operate-Transfer (BOT)

Source of revenues

Availability Payment

TURKEY - "Eurasia Tunnel"

Summary

The project connects the Asian and European sides of istanbul via 5.4 km long two-storey tunnel going underneath the seabed. The project also includes construction of 14.6 km long linking roads 

Current stage

Operation

Duration

25 Years, 11 months

Estimated project cost

$1,2 bn

Greenfield or Brownfield project?

Greenfield

Type of PPP

Build-Operate-Transfer (BOT)

Source of revenues

User Payment

Governmental support

Minimum Demand Guarantee

Exchange Rate Guarantee for Minimum Demand Guarantee

Assumption of Debt in Case of a Default

TURKEY - "Gebze-Orhangazi-izmir Motorway"

Summary

The project consists of 384 km motorway, 49 km linking roads and a 2,7 km. bridge (Osmangazi Bridge which is the fourth longest suspension bridge in the world with mid-span of 1.550 m), 3 tunnels, 38 viaducts

Current stage

Operation

Duration

15 Years and 4 months

Estimated project cost

$6,3 bn

Greenfield or Brownfield project?

Greenfield

Type of PPP

Build-Operate-Transfer (BOT)

Source of revenues

User Payment

Governmental support

Minimum Demand Guarantee

Exchange Rate Guarantee for Minimum Demand Guarantee

Assumption of Debt in Case of a Default