[Social Infrastructure]

AUSTRALIA - ACT Law Courts

Summary

The construction of a new supreme court facility on the site of the existing supreme court and magistrates court buildings. The new construction links the two existing buildings and includes full reconfiguration and refurbishment of the existing, heritage-listed supreme court building

Current stage

Construction

Duration

25 Years

Estimated project cost

$160M

Greenfield or Brownfield project?

Brownfield

Source of revenues

Availability Payments

Volume-based Payments for Some Specific Services

CHINA - Educational Facilities, Equipment and Logistics Outsourcing in Wudang District

Summary

The project consists of the construction and operation of a new nine-year school, a middle school and a kindergarten. The project is the first PPP project in the provincial education system

Current stage

Operational

Duration

13 Years

Estimated project cost

RMB 393.37M

Greenfield or Brownfield project?

Greenfield

Type of PPP

Build-Own-Operate-Transfer (BOOT)

Source of revenues

Availability Payment

Performance Payment

Governmental support

Share of Local Government in Equity Structure

FRANCE - "Projet Biologie-Pharmacie-Chimie"

Summary

The construction of one building of about 60.000 m2 and one building of 15.000 m2 both dedicated to research and education in the fields of biology, pharmacy and chemistry and maintenance of these buildings

Current stage

Construction

Duration

29 Years

Estimated project cost

€300M

Greenfield or Brownfield project?

Greenfield

Type of PPP

Design-Build-Finance-Maintain-Operate (DBFMO)

Source of revenues

Availability Payments

Governmental support

Grant payment

Subsidies

State Guarantees

INDONESIA - Expansion of Dharmais Cancer Hospital

Summary

Located at West Jakarta, the project plans to build with a total area covering 4,400 m2 with 3 Basement, 11 Floors and 194 Beds

Current stage

Feasibility Study

Duration

22 Years

Estimated project cost

$153M

Greenfield or Brownfield project?

Brownfield

Type of PPP

Build-Operate-Transfer (BOT)

Source of revenues

Availability Payment

Governmental support

State Guarantees

MEXICO - Substitution of General Hospital "Aquiles Calles Ramirez" in Tepic, Nayarit

Summary

The project implies building a new general hospital. The private partner will provide operational services

Current stage

Construction

Duration

25 years

Estimated project cost

$72M

Planned procurement method

Open tender

Governmental support

Guarantees on service payments

Type of PPP

Build-Operate-Transfer (BOT)

Greenfield or Brownfield project?

Greenfield

Source of revenues

Availability Payment TURKEY - "Elazig City Hospital"

TURKEY - "Elazığ City Hospital"

Summary

The project includes hospital construction, consisting of a 355,000 square meter facility that will serve up to 20,000 patients and house 1,038 new beds. First green and social bond certified PPP hospital in Turkey

Estimated project cost

$391M

Duration

25 Years

Current stage

Operational

Planned procurement method

PPP

Governmental support

Permission for the Use of Publicly Owned Lands

Exchange Rate Guarantee for Availability Payments

Type of PPP

Built-Lease-Transfer (BLT)

Greenfield or Brownfield project?

Greenfield

Source of revenues

Availability Payment

Guaranteed Minimum Income

Rental income from Commercial Areas

Governmental support

Permission for the Use of Publicly Owned Lands