Phase 0  Planning for contract management

Planning for contract management

The table below lists the activities for the Planning for contract management phase. Your categorisation of your contract based on the complexity and risk profile will determine which activities you should complete.

Activities during contract start-up phase include:

Transactional Contract

Routine Contract

Complex Contract

Strategic Contract

0.1

Assess risk (page 13)

Required

Required

Required

Required

0.2

Develop a contract management plan (page 16)

Not required

Recommended

Required

Required

0.3

Develop risk management plan (page 17)

Not required

Recommended

Strongly Recommended

Required

0.4

Develop other plans if required (page 18)

Not required

Recommended

Recommended

Strongly Recommended

0.5

Consider and manage any contract transition issues (page 18)

Not required

Recommended

Recommended

Strongly Recommended

0.6

Skills development (page 19)

Required (if applicable)

Required (if applicable)

Required (if applicable)

Required (if applicable)

More Information