Key facts

20

number of defence equipment programmes considered in this report, 19 of which are in the Government Major Projects Portfolio

 

£120.3bn

whole-life cost of the major equipment programmes we examined, as at March 2021 (excluding the Future Combat Air System Technology Initiative and Warrior armoured vehicle)

 

19

number of strategic suppliers to the Ministry of Defence (the Department), not all of which directly supply military equipment

Across the projects and programmes we examined, as at March 2021:

8 out of 19

number of programmes where senior responsible owners (SROs) rated programme delivery confidence as 'amber/red' or 'red'

254 months

cumulative forecast net delays, across 13 programmes, in achieving entry into service since going on contract

77 vs 22 months

median running time for the projects and programmes, compared with the median time in post for an SRO

14 out of 19

programmes being procured wholly or partly without competition, only four of which are using this route because of government requirements for manufacture in the UK

58% and 79%

proportion of people working on the Department's Morpheus project and New Style of IT (Deployed) programme teams respectively who are temporary contractors

Around £790 million

the Department's estimate of the monetised benefits that it could deliver if its Strategic Partnering Programme and Category Management programmes are successful