The data says: | • c.65% of projects reported that they did not have a sufficient team to manage expiry |
We also found: | • Insufficient people to manage the totality of operational contract management, expiry and future service provision • Insufficient access to the necessary skills and capabilities - particularly commercial and technical acumen • Where people were available they were typically focussed on future services and not expiry • Teams often cited the lack of people as limiting their ability to focus on expiry |
Learnings: | • CAs need to ensure that projects are properly resourced to manage the complex challenges of expiry • IPA need to consider how PFI expertise can be increased within the public sector and made accessible to CAs |